2.02.005 - PURPOSE.#

This Chapter establishes the Concept Plan review process, submittal requirements, and duties of the Zoning Administrator, Neighborhood Partnership Initiative, and Development Review Committee regarding the review and processing of Concept Plans. The Concept Plan review process is a means for applicants, developers or property owners to receive input from the Zoning Administrator, Neighborhood Partnership Initiative, and Development Review Committee on a proposed development before incurring the costs associated with further stages of the approval process.

(Ord. No. 26-02, Exh. A, 1-20-2026)

2.02.010 - CONCEPT PLAN REQUIRED.#

A Concept Plan is a recommended review process that the applicant may request prior to making application for a Preliminary Plat per Utah State Code 10-20-80.

(Ord. No. 24-01, 1-16-2024; Ord. No. 26-02, Exh. A, 1-20-2026)

2.02.015 - NO VESTING WITH CONCEPT PLAN REVIEW.#

The Concept Plan review does not create any vested rights to proceed with development in any particular configuration and developers may anticipate that the Zoning Administrator, Neighborhood Partnership Initiative, and Development Review Committee will raise other issues not addressed at the concept plan stage.

(Ord. No. 26-02, Exh. A, 1-20-2026)

2.02.020 - SUBMISSION OF APPLICATION.#

A.

Only property owners or their duly authorized agents shall make application for a Concept Plan on forms approved by the Zoning Administrator.

B.

No Concept Plan application shall be processed without the submission of the application and all the supporting materials as required by this Chapter. Incomplete applications shall not be processed under any circumstances. The time frame for when an application shall be submitted in order to be heard first at a Development Review Committee meeting shall be set by policy of the Zoning Administrator.

C.

A Preliminary Plat does not require the submittal of a Concept Plan. If a Concept Plan application is requested by the applicant, a Preliminary Plat may only be submitted once the Concept Plan application has been received and the review process has been completed.

(Ord. No. 24-01, 1-16-2024; Ord. No. 25-01, Exh. B, 1-7-2025)

2.02.025 - FORM AND CONTENTS OF REQUIRED DOCUMENTS.#

The following materials shall be submitted with any application for a Concept Plan. The proposed Concept Plan, drawn to a scale of not more than one (1") inch equals one hundred (100') feet showing the following: 1.

Property boundary with dimensions.

2.

Property owner names and parcel numbers of all adjacent tracts of land.

3.

Locations and widths of existing and proposed streets.

4.

Configuration of proposed lots with minimum and average lot sizes.

5.

Approximate locations, dimensions, and area of all parcels of land proposed to be set aside for park or playground use or other public use.

6.

Those portions of property designated as flood plain and slopes between twenty (20) and thirty (30) percent. See Section 2.06.100.

7.

A summary tabulation table that includes the following information: total acreage for the proposed subdivision, number of lots, and dwelling units per acre.

8.

General topography.

9.

North arrow, stated scale and graphic scale, and date of drawing.

(Ord. No. 24-01, 1-16-2024; Ord. No. 25-01, Exh. B, 1-7-2025)

2.02.030 - REVIEW PROCEDURES.#

The Zoning Administrator shall review each application submitted to determine the completeness of the application. A public meeting will be held with the Neighborhood Partnership Initiative to discuss the land use requirements of development, zoning ordinances, General Plan and applicable City ordinances pertaining to the development prior to proceeding with a Preliminary Plat. At a separate public meeting with the Development Review Committee (DRC) and the developer shall discuss the land use requirements of development, zoning ordinances, General Plan and applicable City ordinances pertaining to the development prior to proceeding with a Preliminary Plat.

(Ord. No. 25-01, Exh. B, 1-7-2025; Ord. No. 26-02, Exh. A, 1-20-2026)

Editor's note— Ord. No. 25-01, Exh. B, adopted January 7, 2025, repealed § 2.02.030, which pertained to public notice and derived from the original Code. Subsequently, Ord. No. 25-01, Exh. B, adopted January 7, 2025, renumbered the former §§ 2.02.035—2.02.045 as §§ 2.02.030—2.02.040. The historical notation has been retained with the amended provisions for reference purposes.

2.02.035 - ENTITLEMENTS.#

The Entitlement associated with a Concept Plan is the eligibility to submit an application for a Preliminary Plat review.

(Ord. No. 25-01, Exh. B, 1-7-2025)

Editor's note— Ord. No. 25-01, Exh. B, adopted January 7, 2025, renumbered the former § 2.02.040 as § 2.02.035.

2.02.040 - APPEALS.#

There is no appeal process with regard to Concept Plans.

(Ord. No. 25-01, Exh. B, 1-7-2025)

Editor's note— Ord. No. 25-01, Exh. B, adopted January 7, 2025, renumbered the former § 2.02.045 as § 2.02.040.