The text
Sec. 4.14.010. - Building department fees.#
1.
Building permit fees: Building permit fees shall be in accordance with the International Building Code (IBC) as adopted by the State of Utah.
2.
Application fee: $25.00.
3.
Deposit (required at time of application): Credited toward permit fee when paid in full, forfeited if plans are withdrawn.
a.
Commercial plans: $300.00
b.
Standard plans: $200.00
c.
Modular or manufactured homes: $100.00
d.
Other structures: $75.00
4.
Building valuations:
a.
Agricultural buildings: $20.00 per square foot
b.
Non-Agricultural.
i.
Commercial Structures per the International Building Code (IBC).
ii.
Residential Structures per the International Residential Code (IRC).
c.
Remodels and Basement finishes: Valuation based on 50% of square feet values from above.
d.
Garages: $49.88 per square foot
e.
Decks: $10.00 per square foot
5.
Building fees:
a.
Agricultural buildings: $6.00 per $1,000.00 of valuation or fraction thereof.
b.
Non-agricultural:
i.
Commercial structures built per the IBC.
ii.
Residential structures built per the IRC
Fees in accordance with Section 1.1.13, Kamas City Building Permit Fees.
6.
Plan review fees:
a.
Agricultural buildings: No fee
b.
Commercial structures: 65 percent of building permit fee
c.
Residential structures: 65 percent of building permit fee
d.
Detached garages with no living space, decks/porches for existing structures, and accessory buildings: 15 percent of building permit fee.
7.
Plumbing permit fees:
a.
Permit issuance fee: $10.00
b.
System fee (does not include $10.00 issuance fee):
i.
Agricultural buildings: $0.035 per square foot
ii.
Commercial structures per the International Plumbing Code (IPC): $0.03 per square foot
iii.
Residential structures per the IRC: $0.03 per square foot
8.
Mechanical permit fees:
a.
Permit issuance fee: $10.00, plus $0.035 per square foot
b.
System fee (does not include $10.00 issuance fee):
i.
Agricultural buildings: $0.03 per square foot
ii.
Commercial structures per the International Mechanical Code (IMC): $0.03 per square foot
iii.
Residential structures per the IRC: $0.03 per square foot
9.
Electrical permit fees:
a.
Permit issuance fee: $10.00
b.
System fee (does not include $10.00 issuance fee):
i.
Agricultural buildings: $0.035 per square foot
ii.
Commercial structures per the National Electric Code (NEC): $0.035 per square foot
iii.
Residential structures per the IRC: $0.035 per square foot
10.
Alternative energy permits: These permits are separate from the permits issued for new construction and are based on 50 percent of the actual permit cost. These permits include, but are not limited to, solar hot water, photovoltaic, geo-thermal, and wind generated power.
a.
Photovoltaic system: $350.00
b.
Geo-thermal: $250.00
c.
Solar hot water: $125.00
d.
Wind generator: $125.00
e.
Permit issuance: Ten percent of review fee
11.
Utah state surcharge: A one percent surcharge on all permits to be collected and remitted to the State of Utah as per U.C.A. § 58-54-9-3, as amended.
12.
Other inspections and fees:
a.
Inspections outside of normal office hours: $100.00 per hour (minimum of one hour)
b.
Re-inspection fee assessed under the provisions of Chapter 1 of both the IBC and IRC: $100.00 per occurrence
c.
Inspections and permits for which no fee specifically indicated: $100.00
d.
Additional plan review required by changes, additions, or revisions to approved plans: $100.00 per hour (minimum of one hour)
13.
Kamas city building permit fees
Total Valuation Fee
Less than $2000 $24 for the first $500 plus $3.50 for each additional $100, or fraction thereof, to and including $2,000
$2,001 to $25,000 $76.50 for the first $2,000 plus $16.50 for each additional $1,000, or fraction thereof, to and including $25,000
$25,001 to $50,000 $456 for the first $25,000 plus $10.10 for each additional $1,000, or fraction thereof, to and including $50,000
$50,001 to $100,000 $756 for the first $50,000 plus $8.50 for each additional $1,000 or fraction thereof, to and including $100,000
$100,000 to $500,000 $1,181 for the first $100,000 plus $6.50 for each additional $1,000 or fraction thereof, to and including $500,000
$500,001 to $1,000,000 $3,781 for the first $500,000 plus $5.50 for each additional $1,000 or fraction thereof, to and including $1,000,000
$1,000,001 and up $6,531 for the first $1,000,000 plus $4.50 for each additional $1,000 or fraction thereof
Fees for inspections not specifically listed shall be determined by the Building Official.
(Ord. 2015-04, 11/10/2015; Res. No. 2022-08, 9/13/2022)
Sec. 4.14.020. - Planning fees.#
1.
Project Fees
a.
Project Application: $200.00
b.
Final Project approval: $200.00
c.
Professional Fees in accordance with Section 1.2.4 below.
2.
Simple lot subdivision fees (due prior to final approval signatures): Dividing one lot in to two lots.
a.
Application/plat review fee: $200.00 per plat
b.
Recording fees: $100.00 plus Summit County Recording Fees
c.
Professional fees in accordance with Section 1.2.4 below.
3.
Subdivision fees (due prior to final approval signatures):
a.
Application fee (concept): $200.00 per plat
b.
Preliminary plat review:
i.
Minor subdivision review: $100.00 per lot plus professional review fees (five lots or fewer).
ii.
Major subdivision review: $200.00 per lot plus professional review fees (six lots or more).
c.
Final plat review: $100.00 per lot plus professional review fees.
d.
Revision to final plat: $1,000.00 per plat plus professional review fees.
e.
Recording fees: $100.00 plus Summit County Recording Fees.
f.
Professional fees in accordance with Section 1.2.4 below.
4.
Professional fees:
a.
Projects which require review by the city attorney, city engineer, or other consultant(s) shall be billed to the applicant at the actual billed rates incurred. At the time of making application to the city for approval of a new subdivision, an applicant shall pay a deposit amount to be used as a credit from which the city may cover the applicant's share of professional fees incurred by the city on an ongoing basis in connection with the application. The deposit amount shall be $300.00 per lot, or $1,200.00, whichever is greater.
b.
The city shall notify the applicant monthly of the amount of costs for professional services incurred by the city in connection with the application, itemized by category of professional services. The city is authorized to immediately use the funds in the applicant's deposit account to pay any outstanding bills for professional services incurred in connection with the application.
c.
If the amount in the applicant's planning deposit account with the city falls below 25 percent of the original amount deposited, the city is authorized to require the applicant to deposit additional funds to bring the account back up to the original amount deposited, or to some lesser amount specified by the city, if the city reasonably believes such funds will be needed to cover professional fees.
5.
Conditional use permit: $300.00
6.
Appeal authority: $500.00. Fee includes appeals to Administrative Law Judge, Planning Commission, or City Council. Professional Fees in accordance with Section 1.2.4. If a court reporter or verbatim transcripts are required, the actual cost will be assessed in addition to the fee.
7.
Reactivation Fee: For projects that have been inactive by the applicant for more than six months a Reactivation Fee of 50 percent of original application fee will be assessed.
8.
Extensions of approvals: $100.00 (in accordance with zoning ordinance provisions and approved by the governing body).
9.
General plan amendments: $500.00 plus professional fees. Fee is nonrefundable and no guarantee of approval of proposed amendment shall be implied by this fee.
10.
Development code amendments: $500.00 plus professional fees. Fee is nonrefundable and no guarantee of approval of proposed amendment shall be implied by this fee.
11.
Zone changes: $1,000.00. Fee is nonrefundable and no guarantee of approval of proposed amendment shall be implied by this fee.
12.
Annexations: $2,000, plus $10.00 per acre. Fee is nonrefundable and no guarantee of approval of proposed annexation shall be implied by this fee.
13.
Sign permit (when required): $50.00
14.
Book and map purchases:
a.
Kamas City General Plan: $50.00
b.
Kamas City Development Code: $50.00
c.
Kamas City Zoning Map: by size
d.
Kamas City Construction Standards: $30.00
e.
Kamas City Centennial History Book: $15.00
15.
Special meetings:
a.
Planning commission: $500.00
b.
City council: $750.00
Any project requesting a special meeting to be convened shall submit a fee for the purpose of scheduling the meeting. In the event the meeting may not be convened due to scheduling conflicts the fee shall be returned to the applicant, less any cost associated with staff time and advertising.
(Ord. 2015-04, 11/10/2015; Res. 2018-06, 9/11/2018; Res. No. 2022-08, 9/13/2022)
Sec. 4.14.030. - Subdivision construction review and inspection fees.#
Projects which require infrastructure installation, whether private or public, shall be required to pay an inspection fee deposit equal to five percent of the estimated construction cost as determined by the city engineer. The city will charge against this deposit all costs associated with the project, including staff, administrative, legal, other professional and engineering consultation fees and costs incurred by the city. If the city has funds remaining after the completion and acceptance of the project by the city, the balance of the fee not used will be refunded to the applicant or developer. If the actual costs associated with the project exceed the deposit, the city shall bill the actual costs to the applicant or developer.
(Ord. 2015-04, 11/10/2015)
Sec. 4.14.040. - Permit to work in city public right-of-way.#
A $25.00 nonrefundable application fee per utility or company, plus a $1,500.00 cash bond for work crossing the street and a $2,000.00 cash bond for every 600 feet of parallel work in the right-of-way (bond to be held for two years after acceptance of repair) plus proof of insurance. Engineering inspection fees or city repair costs may be billed to the licensee or charged against the bond if necessary.
(Ord. 2015-04, 11/10/2015; Res. 2018-06, 9/11/2018)