Cases — 4338675

1 recorded connections shown. Select a record, office or person to follow its source references.

Start with
and connect to

Browse all held record sources

Zoom to read. Drag to explore. Select a connection.

Cases — 4338675

Cases · As of Oct 2, 2026

Cases — 4338675: 1 outgoing connections shown. Point at anyone to see how they are linked.Showing bounded source connections. Dates come from the held records; missing relationships remain unknown.

The source record

As of Oct 2, 2026.

Activity name
DUKE ENERGY - ACO
Case number
05-2015-5003
Case name
DUKE ENERGY - ACO
Region code
05
Fiscal year
2015
Activity type code
AFR
Activity type desc
Administrative - Formal
Activity status code
FOI
Activity status desc
Final Order Issued
Activity status date
2014-10-30
Lead agency
EPA
Case status date
2014-10-30
Voluntary self disclosure
false
Multimedia flag
false
Summary text
U.S. EPA Region 5 issued an Administrative Consent Order (ACO) to Duke Energy Indiana, Inc., Gibson Station to resolve violations of the Clean Air Act (CAA). EPA alleged that Duke exceeded opacity limits for all 5 fossil fueled steam generating units at it's Gibson Station in violation of it's Title V permit, New Source Performance Standards for Fossil-Fuel-Fired Steam Generators at 40 C.F.R. Part 60, Subpart D (for Unit 5 only), and the Indiana State Implementation Plan provisions. EPA issued a NOV/FOV to Duke on June 23, 2011 and July 16, 2013. The ACO requires Duke to install PM CEMS at each of the fossil fueled steam generating units at Gibson Stations (Units 1 thru 5) on or before December 31, 2014. The installation of PM CEMS cost Duke $2 million. Additionally, Duke completed upgrades to their EPS at a cost of $10 million.
Created at
2026-10-02T02:02:59.061315+00:00
Updated at
2026-10-02T02:02:59.061315+00:00